Fiat upravna zgrada - Kragujevac

Execution of demolition and site clearance works on existing surfaces, with the purpose of preparing for the construction of Phase II of the administrative building project for Fiat in Kragujevac. The scope of works included extensive earthworks, construction of water supply and sewage networks, street lighting and other utility installations surrounding the facility, as well as the construction of roads, parking areas, and sidewalks, composite material pathways, landscaping, and complete external site development and furnishing.

The works included the following:

  • Preparatory works
  • Earthworks
  • External fencing
  • Sidewalks, roadways, and traffic signaling
  • Street lighting
  • Landscaping and parking areas
  • Distribution network
  • Water supply system
  • Stormwater drainage system
  • Guardhouse
  • Gates
  • Green areas and urban furniture

Project execution period: 2012.